The air fin cooler division of BGR Energy Systems has secured four contracts for design, engineering and supply of air cooled heat exchangers, aggregating to Rs. 62.20 crore. Two contracts have been secured from Indian Oil Corporation for 15 MMTPA grass root refinery being set up at Paradip, Orissa and another contract from Jindal Steel and Power for 12.5 MTPA integrated steel plant being built at Angul in Orissa and another contract from Technip KT for hydrogen generation unit and diesel hydra-treating unit of the HPCL refinery.
Further, the power projects division of the company has achieved a major milestone by successfully lifting and erecting Boiler Drum weighing 220 ton at a height of 76.5 meters in connection with the 1 x 600 MW Thermal Power Project for Tamil Nadu Electricity Board (TNEB) at Mettur. The boiler structural erection works commenced on 29 September 2009 and Drum Lifting was completed in a record time of just 107 working days.