Artson Engineering has received an order from Overseas AST Co. LLC, Dubai for construction of fuel storage facilities at 3 locations on the outskirts of Abu Dhabi at Al Hamra Military Airport, Safran Air Base and Al Dhafra Air Base of UAE Armed Forces.
The contract scope covers construction of 12 storage ranks and the estimated contract value of the order is about US$ 5.2 million. The time of completion for the total works under this contract shall be 6 months effective from 11 April 2010.
Source :www.biginfotech.in
The contract scope covers construction of 12 storage ranks and the estimated contract value of the order is about US$ 5.2 million. The time of completion for the total works under this contract shall be 6 months effective from 11 April 2010.
Source :www.biginfotech.in